SR-520 Distribution System Improvements

The project involves the replacement of existing 6" and 8" water mains and associated valves and fire hydrants along King and Willard Streets (State Road 520 eastbound and westbound), from Delannoy Street to Forrest Avenue, in the City of Cocoa. Portions of the approximately 2,500 linear foot alignment will be upsize from 6" to 8". The project is intended to improve the water system level of service and reliability as part of the utility’s ongoing capital improvement program.


Status On Hold
Design Start January 2013
Design Completion June 2022
Construction Start TBD
Construction Completion TBD
Spent Budget (Design) $208,074
Total Budget $2,482,876
Percent Construction Complete 0%
                                                  Statistics as of March 2023