Joint Pineda Causeway Pipeline Project

The City of Cocoa and the City of Melbourne are working together to build two parallel, 16-inch water mains along the Pineda Causeway across the Indian River, Merritt Island, and the Banana River.  The City of Cocoa's portion of the joint project consists of the installation of approximately 20,000 feet of water main and provides hydraulic and water quality improvements to the distribution system.

The City of Melbourne oversees the payment distribution to the contractor for the project as construction progresses.


Status Construction
Design Start October 2017
Design Completion August 2021
Construction Start December 2021
Construction Completion December 2023
Spent Budget $13,595,572
Total Budget $14,010,421
Percent Construction Complete 98%

                                                  Statistics as of September 2023