ATS Replacement at TCR Pump Station

The project includes the replacement of the ATS at the TCR Pump Station which upon a power outage starts the backup power generator and transfers the power feed to the pumps from the main utility to the generator.  The ATS failed over a year ago and an assessment was conducted which concluded it was not repairable.

Status Completed
Start April 2018
Completion May 2019
Spent Budget $832,036
Total Budget $903,543
Percent Complete 100%

Project Completed